Kickoff Meeting - September 10, 2018
Progress Meeting - October 23, 2018
Submit Draft Baseline Hydrology - December 14, 2018
Comment Review Meeting - January 14, 2019
Final Baseline Hydrology Approved - February 4, 2019
Submit Draft FHAD - April 29, 2019
Comment Review Meeting - August 5, 2019
Submit Model - September 2019
Submit 100-year Floodplain - December 2019
Submit Floodway and 500-year Floodplain - August 2020
Submit Full FHAD Review - August 2021
Final FHAD Submittal - October 2021